Installation range: wooden floor, marble, ceramic tile, cement floor. Basic requirements:
flatness within 2 m error less than 5 mm. The surface is uniform, no solid wheel
track, crack, bad side, water, no sand.
Shop installs methods:
1. The shop installs the ground must level off, clean, no dust. 2. According to
the floor of the Numbers them in chronological order, alignment, pay attention to
in the process of merger shop to the field line alignment. 3. Along the GeFeng sanctions
adjacent open two slices of floor, will manufacturers of professional connection
with GeFeng place on the underside, in connection with the surface brushing glue.
The first one board stuck half, and then the other connecting strap a board stuck
in the rest of the connection, will close on crack can. (mobile installation) welding
heat welding method bend-we suggest using force the company production of professional
welding line, the floor before welding, first with manual or machine in the floor
surface slot, lane slot place must clean up the temperature, heat welding is not
lower than 300 ℃, and the automatic welding equipment or manual operation. Before
the first official welding, with a short welding welding to test the temperature
and speed of the appropriate. Weld after two steps, but remove excess welding. Use
first crescent spade spade off raised portion of welding half, stay welding sufficient
cooling, shovel to rest.